CMS - Underground
Construction
Projects
Centennial Coal - Mandalong Coal Clearance
System.
The system was designed to handle the coal from
the New Mandalong Longwall and 3 continuous miner units. Coal is
conveyed from the seam via 350m of stone drivage to the top of the
2000t capacity surge bin some 35m above. The coal is then metered
via a conical hopper system into 2 x 2000t/hour vibro feeders that
controls the coal flow to both Delta and Eraring Power Stations.
Eraring utilizes the old Cooranbong workings to deliver the coal
into the screening plant on the Cooranbong surface some 12km away,
before being sent to the power station via the overland conveyors.
Delta coal goes via the newly commissioned 4.5km
underground conveyor system to be screened and delivered onto the
overland conveyor system at the Train unloader station on Rutleys
Road. The project was divided into several major mining contracts.
Surge bin access roads, surge bin shaft construction, manufacture
and installation of the surge bin metering hoppers and feeders and
the extension of the Delta production unit workings to intercept
the surface drift. Our staff has been involved with all the contracts
with the exception of the surface drift.
Surge Bin Access Roadways
This was a 6.5m x 2.8m roadway, driven in stone
at a gradient of 1 in 6. The companies Mitsui S200 handled the mining
work in the single entry drivage to the top of the surge bin and
then constructed the shaft top chamber. In addition to this preliminary
drivage we also constructed the first overcasts for No 1 longwall
return and the Main Gate belt drive.
The underground access roads to the Mandalong surface
drift along with 260m of the 1 in 8 drift, to assist in the timing
of the project and finally 1000m of brushing to allow the Longwall
supports to be transported to the face line.
Surge Bin Shaft Construction
The shaft was 10.5m finished diameter and 35m deep.
An initial 2.7m shaft was raised through the bunker section from
the surface and the shaft widened by drill and blast. A 1m diameter
raise bore was lined through to the surface to allow the top of
the surge bin to be ventilated. Service pipes were installed and
compressed air and shot crete were supplied direct from the surface.
A purpose designed winding system was utilized
for the construction allowing man and material access for the drilling,
blasting, support and shotcreting to be carried out in safety.
Surge Bin Steelwork Manufacture and Installation
The steel work was designed by SKM, H&M engineering
manufactured the steel work and Ludowici supplied the feeders. The
complex steelwork was installed utilizing the construction winding
system, there was very little tolerance in the design. Sections
of the steel hopper had to be placed exactly in position will only
millimeters to spare. The final survey showed a vertical error of
3mm.
Delta Drivage
Initially it was thought the drivages could be
taken entirely in the seam and 4 headings were driven to take advantage
of the production after 2000m faulting caused a rethink, at this
stage it was decided to carryout the work by contract and allow
the mines production miners to carry on with the longwall and mains
development program.
The first fault zone was a 6m down throw fault
carried out with the Mitsui S200. The second zone was a 12m up throw
which placed Great Northern conglomerate into the working, despite
the conglomerate being at the absolute limit of the Mitsui S200,
the 250m of stone work was completed. A total of 1600m of drivage
was under taken, 400m of which was in some very poor geological
conditions, and 950m were carried out under single entry conditions.
The coal work was done with a Dash 3 miner.
Copyright© 2008 CMS, all rights reserved.
Underground Construction, NSW Australia
Website designed by MaoWebstyle
|